| Peregrine
scrubs at wash-resistant costs
2007-07-27 17:13 ET - Street Wire
by Will Purcell
Eric Friedland's Peregrine Diamonds
Ltd. thinks it can lower projected
mining costs at its DO-27 project, but
reductions will not be proportional to
the amount of waste material washed away
during the company's scrubbing
experiment. That will be disappointing
to investors expecting operating costs
will be as easy to wash away as the
kimberlite fines. Still, lower costs
should help Peregrine avoid a bulk
sample bust at the big pipe once called
Tli Kwi Cho.
The plan
In a press release issued July 24,
Peregrine said it managed to remove
approximately two-thirds of the fine
bits of material from its kimberlite by
washing the rock. The effect was most
apparent in the upper 60 metres of the
kimberlite, where scrubbing removed 90
per cent of the waste rock, and least
effective at depth. Expectations of
comparable reductions in operating and
capital costs are unrealistic.
Removing that waste material and
keeping most of the diamonds could
effectively increase the grade of the
material going to a processing plant by
a factor of three. Mr. Friedland offers
further encouragement, stating that the
scrubbing test used water at normal
pressure and Peregrine now plans to
experiment with using high-pressure
systems to improve its waste separation.
As a result, Peregrine believes it may
be able to achieve an enhancement of up
to five times the grade of the original
kimberlite.
That could have a big impact on the
economics of the DO-27 project, but
operating costs are unlikely to drop
more than 50 per cent. All the rock
would still have to be mined, but mining
costs in an open pit mine in the area
are likely to be no more $4 (U.S.) per
tonne. The scrubbing would introduce a
new cost, but it would likely add just
$3 (U.S.) per tonne to the operating
expenses. The company would also face
the issue of what to do with the waste
material -- effectively kimberlite mud
-- and that would add something to the
operating costs.
The big saving would come on the
personnel and processing side. If Mr.
Friedland's optimistic waste reduction
estimate holds up, Peregrine would send
just one-fifth the amount of kimberlite
off for processing, allowing it to run
with a much smaller plant. A smaller
plant would have higher costs per tonne
than a larger one, but Peregrine's plant
costs could easily drop to about
one-third of what they would otherwise
be.
The implications
Operating costs at Diavik are running
at under $100 per tonne, and Jericho
still hopes to hit a target of about $85
per tonne. Earlier, Mr. Friedland said
he believed DO-27 needed rock worth at
least $70 per tonne to break even,
before Peregrine set out to lower its
anticipated costs. That figure may be on
the optimistic side, but if Peregrine is
able to achieve operating costs of no
more than $45 per tonne, it would take
an unpleasant surprise for the result of
the company's current bulk test to kill
the project.
Based on earlier mini-bulk tests,
Peregrine expects a grade of about 0.9
carat per tonne from the core of its
kimberlite pipe, with grades of perhaps
one-half carat per tonne in other fringe
phases of rock. Mr. Friedland believes
those earlier results are
representative, and Peregrine is
expecting few grade surprises from the
2,650-tonne test it is currently
processing.
The original 1994 test produced a
diamond value that would likely be no
more than $40 (U.S.) per carat in
today's dollars, and Peregrine needed an
optimistic modelled value to push its
projected value to $70 (U.S.) per carat.
Although diamond values remain critical
to the project, a somewhat higher value
is possible and the scrubbing success
could offer valuable breathing room.
Peregrine closed down three cents to
$1.55 Thursday on 33,000 shares. |